Metro Fiber Backbone Expansion

A 96-count metro fiber ring linking three central offices — surveyed, spliced, tested, and handed to operations without a single unplanned maintenance window.

Role:Associate Network Engineer Timeline:8 months Domain:Fiber · DWDM · OSP
Blue fiber cables terminated into connectors on a distribution block in a data center

Project Overview


Capacity on the east-metro corridor was running hot, and single-homed enterprise customers had no diverse path during fiber cuts. The program added a fully diverse ring across three central offices with hand-off capacity for DWDM growth.

I owned the engineering package end to end: route validation, splice schematics, loss budgets, contractor coordination, and the acceptance test plan signed off by operations.

Scope:3 offices · 41 route miles
Plant:96-count single-mode
  • •OTDR + OLTS acceptance testing
  • •GIS route records & as-builts
  • •Zero unplanned outages at cutover

The Challenge


Two offices shared a single physical path along a rail corridor, so one backhoe event could isolate both. Permitting for the diverse route crossed county roads, a canal, and a congested downtown duct bank with almost no spare innerduct.

  • Single physical path serving two central offices with no diverse backup for enterprise SLA circuits.
  • Downtown duct bank at 90% fill, requiring a pull-through plan that avoided disturbing live cables.
  • Cutover windows limited to 12am–4am maintenance slots with full rollback plans required.

Approach & Delivery


1 · Survey & design

Walked every manhole on the proposed route, rodded questionable ducts, and re-routed two segments around collapsed conduit. Produced splice schematics, loss budgets per span, and a phased construction schedule.

2 · Build & test

Coordinated splicing crews across night shifts, witnessed OTDR traces bidirectionally, and rejected two spans that missed the loss budget until they were re-spliced clean.

3 · Migration

Moved enterprise circuits in small batches with per-circuit rollback checkpoints. NOC watched error counters live; every migration completed inside its window.

4 · Handover

Delivered GIS as-builts, updated fiber records, OTDR libraries, and a ring-protection test report. Ran a lunch-and-learn so NOC techs knew the new protection paths by heart.

Outcomes & Deliverables


  • Fully diverse ring in service with documented sub-50ms protection switching on every tested path.
  • Every span inside its loss budget, with a complete OTDR and light-level test library archived for future troubleshooting.
  • GIS as-builts, splice records, and runbooks handed to operations — plus a repeatable acceptance template now used on the next two builds.
Single-mode OS2OTDR / OLTSDWDM-readyGIS recordsAnsible inventory